1. INTRODUCTION

– Establishment Decision No. 3590/QĐ-UBND, issued on 21st August 2007 by Binh Duong People’s Committee to rename Dat Cuoc Ceramic Industrial Zone to Dat Cuoc IP;

Investment Certificate No. 46221000275 issued by Management Board of Binh Duong Industrial Parks, on 3 rd October 2007.

– Decision No. 3430/QĐ-UBND, dated on 8th August 2007 by Binh Duong People’s Committee to correct the master plan in detail (phrase 2, scale 108.9 ha); No. 609/QĐ-UBND, dated on 11th February 2010 by Binh Duong People’s Committee to approve the correction in master plan, proportion 1/2000 – Phrase 1 – Tan Uyen District, Binh Duong province.

3. STRUCTURE OF LAND USE

Type of Land

Area (ha)

Percentage(%)

Land for industrial factories

130,90

61,502

Land for storage, management office

4,08

1,917

Land for parks – lakes

31,92

14,997

Land for major infrastructure facilities

5,66

2,659

Land for roads

28,84

13,550

Total

212,84

100

– Location: 20 km away from ICD Song Than, 50 km from Cat Lai port, 55 km from Tan Son Nhat airport, 25 km from 1A Highway, 18 km from Binh Duong Ave, 12 km from Song Than, 52 km to HCM city and 25 km to Bien Hoa city.

– Total investment capital: 238.597 billion VND.

– Leasing industrial Land: 130,11 ha; Land for service: 40,3 ha.

– Plant for Centralized wastewater treatment: daily capacity 20,000 m3 , first phrase: daily capacity 2,800 m3.

– Operative year: October 2007.

– Total implementing capital: 179.3 billion VND.

– Re-Leasing land: 49.73 ha, filled land percentage 38%.

– Land re-leasing Price (reference): from 780,000 VND/m2 to 975,000 VND/m2 (not include infrastructure using fees.)